What do you do if your company wants to grow, but the grid operator won’t be able to provide additional power for several years? The Wildenburg Business Park was faced with a wait until 2029 with Fluvius for the necessary upgrade to 850 kVA. Without additional power, commissioning the new production hall was technically impossible.
EnergyKing implemented a fast and forward-looking solution by installing five Sungrow PowerStacks ( 550 kW / 1,145 kWh). This battery system acts as a local energy buffer that immediately absorbs peaks exceeding the current grid capacity of 630 kVA. Thanks to the smart flex control provided by partner Imby, the batteries are charged at optimal times to deliver the necessary extra power during the day.
The result? The new production facility is immediately operational, and business continuity at the site is ensured. Wildenburg proves that smart battery storage is the solution for avoiding grid congestion and ensuring economic growth.